Overview of Key Changes to TGD L – Dwellings 2019


Technical Guidance Documents are published to accompany each part of the Building Regulations in Ireland indicating how the requirements of that part can be achieved in practice.

Technical Guidance Document L (TGD L) indicates the requirements for Conservation of Fuel and Energy.

A new TGD L is due to be published in 2019. The new document follows a revision of the Energy Performance of Buildings Directive (EPBD). Member States have until March 2020 to translate into national law all the new requirements from the EU energy efficiency legislation affecting buildings.

Draft Transitional Arrangements:

  • NZEB and TGD L 2019 Dwellings to apply to new Dwellings commencing construction from 1st November 2019 subject to transition.
  • Transitional arrangements to allow TGD L 2011 – Dwellings to be used where planning approval or permission has been applied for on or before 31st October 2019 and substantial completion is completed within 1 year i.e. by 31st October 2020.

Overview of key changes to TGD L Dwellings 2019:

  • Introduction of NZEB (Nearly-Zero Energy Building), MPEPC (Maximum Permitted Energy Performance Coefficient)=0.30, MPCPC (Maximum Permitted Carbon Performance Coefficient)=0.35
  • Introduction of Major Renovations to a cost optimal level where technically, economically and functionally feasible
  • Introduction of a Renewable Energy Ratio (RER) of 20% as per ISO EN 52000 (to replace 10kWh/m2 /yr).
  • Reduction of air permeability backstop from 7m3 /hr/m2 to 5m3 /hr/m2
  • Table 1- Reduction of wall and floor backstop U-Value from 0.21W/m2K to 0.18 W/m2K
  • Table 1- Reduction of window backstop U-Value from 1.6 W/m2K to 1.4 W/m2K
  • Inclusion of guidance to avoid overheating in dwellings
  • Par 1.3.2.5 – removal of variation of U-Value with percentage glazing • Introduction of calculation of Ru value for corridors in apartments.

The draft TGD L – Dwellings 2019 can be accessed here.

The current TGD L – Dwellings 2011-2017 can be accessed here.

Minimum BER rating for new houses built in 2019.

What is a Building Renovation Passport?


In its most recent study, the Buildings Performance Institute Europe (BPIE) suggests to evolve EPCs into Building Renovation Passports. Based on three examples of “Building Renovation Passports” in the Belgian region of Flanders (“Woningpas”), France (“Passeport Efficacité Énergétique”) and Germany (“Individueller Sanierungsfahrplan”),  building renovation passport are centred around the combination of technical on-site energy audits and quality criteria established in dialogue with building owners. The result is a user-friendly long-term roadmap that owners can use to plan deep renovations, gather all relevant building information in a sole place and get an up-to-date screenshot of the building across its lifetime, with information about comfort levels (air quality, better daylight entry, etc.) and potential access to finance.

A Building Renovation Passport (BRP) is a document – in electronic or paper format – outlining a long-term (up to 15-20 years) step-by-step renovation roadmap to achieve deep renovation for a specific building. It is designed to reflect the (changing) situation of the owner or occupier. The BRP also addresses the complexity of renovation works and ensures coordination throughout the different stages.

Building Renovation Passport – Overview of its components (Source: BPIE)

A Building Renovation Passport is an evolution of the Energy Performance Certificate (EPC), as it supports building owners with personalised suggestions on their renovation options. These result from an on-site energy audit fulfilling specific quality criteria and indicators established in dialogue with the owner. Via BRPs, building owners receive a ready-to-use, personalised renovation plan, presenting all the measures to be taken and the related expected benefits, including energy savings and comfort improvement.

EuroACE’s recommendation 5 on the Amended Energy Performance of Buildings Directive (EPBD) 2018 recommends the introduction of Building Renovation Passports as a tool to inform, motivate and incite building owners to undertake energy renovation is a manner by which national and regional governments can bring tangible support to consumers, thus boosting energy renovation rates and depths.

Member States have until March 2020 to translate into national law all the new requirements from the EU energy efficiency legislation affecting buildings.

Lets wait to see if the Building Renovation Passports will be introduced in Ireland or not.

Minimum BER Rating for New Houses Built in 2019

 

We are quickly approaching the introduction of Nearly-Zero Energy Buildings (nZEB) standard and once again we are asked to improve the energy performance of buildings.

 

What is a Nearly-Zero Energy Building (nZEB)?

‘Nearly zero-energy building’ means a building that has a very high energy performance. The nearly zero or very low amount of energy required should be covered to a very significant extent by energy from renewable sources, including energy from renewable sources produced on-site or nearby.

When will the new regulations be introduced?

Article 9(1) of Directive 2010/31/EU of the European Parliament and of the Council of 19 May 2010 on the energy performance of buildings requires that all new buildings:

– shall be nearly-zero energy buildings by 31 December 2020;

– occupied and owned by public authorities shall be nearly zero energy buildings after 31 December 2018

A full review of Part L of the Building Regulations is expected to be published very soon, this will include the nZEB standard.

What are the transitional arrangements?

This will be confirmed when the reviewed Part L of the Building Regulations is published.

The draft transitional arrangements required the standard to apply to all new dwellings commencing construction from 1st April 2019 (subject to transition).

Transitional arrangements (draft) will allow Part L-2011 Dwellings to be used when planning permission has been applied for prior to the application date of 1st April 2019 and substantial work * is completed by 31st March 2020.

*The structure of the external walls has been erected.

 

How will compliance with nZEB be demonstrated?

For domestic buildings, compliance will be demonstrated using the DEAP methodology. DEAP is currently being updated to account for NZEB.

For non-domestic buildings, compliance will be demonstrated using the NEAP methodology.

 

Is nZEB standard only for new houses?

No, the new standard applies to Domestic and Non Domestic Buildings.

It also applies to existing buildings (Domestic and Non Domestic) where major renovations take place.

Major Renovation’ means the renovation of a building where more than 25% of the surface area of the building envelope undergoes renovation.

For Existing Non Domestic Buildings this will require that the building is brought up to cost optimal level, which is defined in the building regulations as:

  • Upgrade Heating System more than 15 years’ old
  • Upgrade Cooling and Ventilation Systems more than 15 years’ old
  • Upgrade Lighting more than 15 years old.

For Existing Domestic Buildings, it is proposed that major renovation is typically activated where external wall is renovated. The cost optimal level is a primary energy performance of 125 kWh/m2/yr when calculated using DEAP or upgrade of roof insulation and heating system.

 

What are the BER requirements once nZEB standards are implemented?

This is currently out for public consultation, refer to Department of Housing, Planning and Local Government website for proposed changes to the regulations and DEAP methodology.

For all new builds, it is proposed that nZEB will be equivalent to a 25% improvement in energy performance on the 2011 Building Regulations.

This equates to an energy performance and carbon performance parameter that is 70% better than Ireland’s 2005 standard.

A new Nearly-Zero Energy Building (Dwelling) will typically correspond to an A2 Building Energy Rating (BER).

 

 

Will a new house be more expensive to build from 1st April 2019?

The impact on design and cost is expected to be relatively small.

The projected increase is 1.9% over current construction costs depending on the dwelling archetype and design specification applied.

 

 